P920 BACHELOR HEADQUARTERS
الموقع DJIBOUTI
العام 2014-2015
حالة العمل The project had been completed and delivered in working condition in June, 2015
العمل المنفذ The Building Management System had been established to control and trace the HVAC system which is consist of DOAS's, air conditioning units, PTAC units and domestic hot water system. The scope of the project is to produce DDC - MCC panels, mechanical installation of the field equipments, cable connections, programming of the controllers and startup the whole system.
عدد نقاط التحكم 1072 I/O and Bacnet integration
MOSUL 200 BED STATE HOSPITAL
الموقع Mosul - Iraq
العام 2014
حالة العمل HVAC BMS had been comleted in May, 2014
العمل المنفذ The Building Management System had been established to control and trace the HVAC system which is consist of 20 AHU's, hot water boilers and hot water circulation pumps, chillers and chilled water pumps and chilled water system and other mechanical equipments. This BMS was carried out by Johnson Controls field equipments and controllers and Metasys software. The DDC panel production, mechanical installation of the field equipments, cable connections, programming of the controllers and startup is made by us.
عدد نقاط التحكم 890 I/O
ALKHAIRAT POWER PLANT
الموقع Karbala - Iraq
العام 2014
حالة العمل HVAC automationsystem had been comleted in March, 2014
العمل المنفذ The HVAC Automation System had been established to control and trace the HVAC system which is consist of 11 AHU's. The DDC panel production, mechanical installation of the field equipments, cable connections, programming of the controllers and startup is made by us.
عدد نقاط التحكم 190 I/O
PRESIDENTIAL INFORMATION AND COORDINATION CENTER
الموقع Kabul - Afghanistan
العام 2014
حالة العمل HVAC BMS had been comleted in March, 2014.
العمل المنفذ The Building Management System had been established to control and trace the HVAC system which is consist of 14Rooftop Units ( RTU ). This BMS was carried out by Johnson Controls field equipments and controllers and Metasys software. The DDC panel production, mechanical installation of the field equipments, cable connections, programming of the controllers and startup is made by us.
عدد نقاط التحكم 140 I/O
KONYA AIRPORT
الموقع Konya - TURKEY
العام 2014
حالة العمل HVAC BMS had been comleted in August, 2014.
العمل المنفذ The Building Management System had been established to control and trace the HVAC system which is consist of 14 AHU's, hot water boilers and hot water circulation pumps, chillers and chilled water pumps and chilled water system and other mechanical equipments. This BMS was carried out by Johnson Controls field equipments and controllers and Metasys software. The DDC panel production, mechanical installation of the field equipments, cable connections, programming of the controllers and startup is made by us.
عدد نقاط التحكم 480 I/O
HOLIDAY INN HOTEL
الموقع Gaziantep - TURKEY
العام 2013
حالة العمل HVAC BMS had been comleted in December, 2013.
العمل المنفذ The Building Management System had been established to control and trace the HVAC system which is consist of 10 AHU's, hot water boilers and hot water circulation pumps, chillers and chilled water pumps and chilled water system and other mechanical equipments. The DDC-MCC panel production, mechanical installation of the field equipments, cable connections, programming of the controllers and startup is made by us.
عدد نقاط التحكم 650 I/O
MARDIN ARTUKLU UNIVERSITY CAMPUS CONFERENCE HALL
الموقع Mardin - TURKEY
العام 2014
حالة العمل HVAC automationsystem had been comleted in September, 2014.
العمل المنفذ The HVAC Automation System had been established to control and trace the HVAC system which is consist of 6 AHU's. The DDC panel production, mechanical installation of the field equipments, cable connections, programming of the controllers and startup is made by us.
عدد نقاط التحكم 150 I/O
TURKISH EMBASSY BUILDING
الموقع Naxcivan - NAXCIVAN
العام 2013
حالة العمل HVAC BMS had been comleted in November, 2013.
العمل المنفذ The Building Management System had been established to control and trace the HVAC system which is consist of 5 AHU's, hot water boilers and hot water circulation pumps, chillers and chilled water pumps and chilled water system, VRV system and other mechanical equipments. This BMS was carried out by Johnson Controls field equipments and controllers and Metasys software. The DDC panel production, mechanical installation of the field equipments, cable connections, programming of the controllers, Bacnet integration for VRV and startup is made by us.
عدد نقاط التحكم 1400 I/O
RADIOTHERAPY HOSPITAL
الموقع Basrah - Iraq
العام 2013
حالة العمل HVAC BMS and Bulding Security Management had been comleted in November, 2013.
العمل المنفذ The Building Management System had been integrated with the building weak current system which is consist of CCTV, access control, fire alarm system, public address and voice alarm, tv system, IP phone system. The Integrated Building Management System is established to control and trace the HVAC system which is consist of 2 AHU, hot water boilers and hot water circulation pumps, chillers and chilled water pumps and chilled water system and other mechanical equipments. This BMS was carried out by Johnson Controls field equipments and controllers and Metasys software. The DDC panel production, mechanical installation of the field equipments, cable connections, programming of the controllers, Bacnet integration for weak current system and startup is made by us.
عدد نقاط التحكم 250 I/O
RADIOTHERAPY HOSPITAL
الموقع Hillah - Iraq
العام 2013
حالة العمل HVAC BMS and Bulding Security Management had been comleted in November, 2013.
العمل المنفذ The Building Management System had been integrated with the building weak current system which is consist of CCTV, access control, fire alarm system, public address and voice alarm, tv system, IP phone system. The Integrated Building Management System is established to control and trace the HVAC system which is consist of 2 AHU, hot water boilers and hot water circulation pumps, chillers and chilled water pumps and chilled water system and other mechanical equipments. This BMS was carried out by Johnson Controls field equipments and controllers and Metasys software. The DDC panel production, mechanical installation of the field equipments, cable connections, programming of the controllers, Bacnet integration for weak current system and startup is made by us.
عدد نقاط التحكم 250 I/O
RADIOTHERAPY HOSPITAL
الموقع Ramadi - Iraq
العام 2013
حالة العمل HVAC BMS and Bulding Security Management had been comleted in November, 2013.
العمل المنفذ The Building Management System had been integrated with the building weak current system which is consist of CCTV, access control, fire alarm system, public address and voice alarm, tv system, IP phone system. The Integrated Building Management System is established to control and trace the HVAC system which is consist of 2 AHU, hot water boilers and hot water circulation pumps, chillers and chilled water pumps and chilled water system and other mechanical equipments. This BMS was carried out by Johnson Controls field equipments and controllers and Metasys software. The DDC panel production, mechanical installation of the field equipments, cable connections, programming of the controllers, Bacnet integration for weak current system and startup is made by us.
عدد نقاط التحكم 250 I/O
TITANIC OTEL
الموقع Sulaymaniyah - Iraq
العام 2011-2013
حالة العمل HVAC BMS had been comleted in August, 2013.
العمل المنفذ The Building Management System had been established to control and trace the HVAC system which is consist of 18 AHU's, hot water boilers and hot water circulation pumps, chillers and chilled water pumps and chilled water system and other mechanical equipments. The DDC-MCC panel production, mechanical installation of the field equipments, cable connections, programming of the controllers and startup is made by us.
عدد نقاط التحكم 370 I/O
400 BED STATE HOSPITAL
الموقع Adana - TURKEY
العام 2011-2012
حالة العمل HVAC BMS had been comleted in August, 2011.
العمل المنفذ The Building Management System had been established to control and trace the HVAC system which is consist of 34 AHU's, hot water boilers and hot water circulation pumps, chillers and chilled water pumps and chilled water system and other mechanical equipments. This BMS was carried out by Johnson Controls field equipments and controllers and Metasys software. The DDC panel production, mechanical installation of the field equipments, cable connections, programming of the controllers and startup is made by us.
عدد نقاط التحكم 1600 I/O
ERDOBA ELEGANCE 5 STARS HOTEL
الموقع Mardin - TURKEY
العام 2011
حالة العمل HVAC BMS had been comleted in 2011.
العمل المنفذ The Building Management System had been established to control and trace the HVAC system which is consist of 17 AHU's, hot water boilers and hot water circulation pumps, chillers and chilled water pumps and chilled water system and other mechanical equipments. This BMS was carried out by Johnson Controls field equipments and controllers and Metasys software. The DDC panel production, mechanical installation of the field equipments, cable connections, programming of the controllers and startup is made by us.
عدد نقاط التحكم 625 I/O
SAID HAMDINE LAW FACULTY
الموقع Algeria
العام 2013
حالة العمل HVAC BMS had been comleted in December, 2013.
العمل المنفذ The Building Management System had been established to control and trace the HVAC system which is consist of 34 AHU's, hot water boilers and hot water circulation pumps, chillers and chilled water pumps and chilled water system and other mechanical equipments. This BMS was carried out by Johnson Controls field equipments and controllers and Metasys software. The DDC panel production, mechanical installation of the field equipments, cable connections, programming of the controllers and startup made by us.
عدد نقاط التحكم 1100 I/O
MEDLINE HOSPITAL
الموقع Adana - TURKEY
العام 2009
حالة العمل HVAC BMS had been comleted in 2009.
العمل المنفذ The Building Management System had been established to control and trace the HVAC system which is consist of 22 AHU's, hot water boilers and hot water circulation pumps, chillers and chilled water pumps and chilled water system and other mechanical equipments. This BMS was carried out by Johnson Controls field equipments and controllers and Metasys software. The DDC panel production, mechanical installation of the field equipments, cable connections, programming of the controllers and startup is made by us.
عدد نقاط التحكم 700 I/O
CUKUROVA UNIVERSITY BALCALI HOSPITAL EMERGENCY DEPT.
الموقع Adana - TURKEY
العام 2011
حالة العمل HVAC Automation had been comleted in 2011.
العمل المنفذ The Automation system had been established to control and trace the AHU's . The DDC panel production, mechanical installation of the field equipments, cable connections, programming of the controllers and startup is made by us.
عدد نقاط التحكم 150 I/O
HILLAH 400 BED STATE HOSPITAL
الموقع Hillah - Iraq
العام 2014-2015
حالة العمل The project was started in January, 2014 and completed in 2015. Type of work: Supervision for BMS and low current systems, programming and commissioning of the systems.
العمل المنفذ
عدد نقاط التحكم 3200 I/O
MERSIN CENTRAL BUS STATION
الموقع Mersin - TURKEY
العام 2015
حالة العمل Fire Alarm System and HVAC Automation is comleted in March, 2015.
العمل المنفذ The terminal building is equipped with the smoke evacuation windows. The main purpose of the automation system is to provide open the smoke evacuation windows automatically when a fire alarm is active. The BMS is established to trace the fire fighting system pumps and butterfly valves and water tank level etc. If a fire alarm is activated the BMS will sent SMS to inform the City Fire Protection Department
عدد نقاط التحكم 105 I/O
HATEM HOSPITAL
الموقع Gaziantep - TURKEY
العام 2015
حالة العمل The project is started in January, 2015 and completed in June, 2015.
العمل المنفذ The Building Management System is established to control and trace the HVAC system which is consist of 13 AHU's, hot water boilers and hot water circulation pumps, chillers and chilled water pumps and chilled water system and other mechanical equipments. This BMS was carried out by Johnson Controls field equipments and controllers and Metasys software. The scope of the project is to produce DDC-MCC panels, mechanical installation of the field equipments, cable connections, programming of the controllers and startup the whole system.
عدد نقاط التحكم 676 I/O and Bacnet MS/TP integration points.
KILIS STATE HOSPITAL
الموقع Kilis - TURKEY
العام 2015
حالة العمل HVAC BMS is comleted in March, 2015.
العمل المنفذ The Building Management System is established to control and trace the HVAC system which is consist of 7 AHU's, hot water boilers and hot water circulation pumps. This BMS was carried out by Johnson Controls field equipments and controllers and Metasys software. The DDC panel production, mechanical installation of the field equipments, cable connections, programming of the controllers and startup is made by us
عدد نقاط التحكم 200 I/O
CARREFOUR SHOPPING MALL
الموقع DUHOK - IRAQ
العام 2014
حالة العمل The project is completed and delivered in working condition in June, 2015
العمل المنفذ The Building Management System is established to control and trace the HVAC system which is consist of AHUs, fan coil units ant the other HVAC units. This BMS was carried out by Johnson Controls field equipments and controllers and Metasys software. The scope of the project is to produce DDC panels, mechanical installation of the field equipments, cable connections, programming of the controllers and startup the whole system.
عدد نقاط التحكم 800 I/O
COMPOUND REHAB NIAMEY
الموقع Niamey, NIGER
العام 2014-2015
حالة العمل The project is completed and delivered in working condition in May, 2015
العمل المنفذ The Building Management System is established to control and trace the HVAC system which is consist of AHUs, chillers and chilled water pumps,ventilation units and generator fuel system. The scope of the project is to produce DDC panels, mechanical installation of the field equipments, cable connections, programming of the controllers and
عدد نقاط التحكم 350 I/O and Modbus integration
NEOPLIS HOTEL
الموقع AYAS-MERSIN
العام 2015
حالة العمل The project is completed in Jun, 2016
العمل المنفذ The Building Management System established to control and trace the HVAC system which is consist of AHUs, water source heat pumps and hot water circulation pumps, VRF system and the other mechanical equipments. Scope of the work is The DDC-MCC panel production, mechanical installation of the field equipments, cable connections, programming of the controllers, VRF integrations and startup the whole system via the BMS.
عدد نقاط التحكم 2.410 I/O and Bacnet integration points.
AGHTIA ALPIN NATUREL SPRING WATER
الموقع POZANTI - ADANA / TURKEY
العام 2015
حالة العمل The project is started in June, 2015 and completed at the end of 2015
العمل المنفذ BMS: The Building Management System had been established to control and trace the HVAC system which is consist of AHUs, hot water boilers and hot water circulation pumps, chillers and chilled water pumps and the other mechanical equipments. This BMS will be carried out by Johnson Controls field equipments and controllers and software. DDC panel production, mechanical installation of the field equipments, cable connections, programming of the controllers and startup is made by us. SECURITY SYSTEM: Closed Circuit Television System - CCTV Public Address and Voice Alarm System Fire Alarm System had been installed and startup by us.
عدد نقاط التحكم 150 I/O points and Bacnet MS/TP integration points.
MAJIDIMALL SHOPPING MALL
الموقع Suleimania - N. Iraq
العام 2015-2016
حالة العمل The project is signed in September, 2015 and completed in 1st quarter of 2016.
العمل المنفذ BMS: The Building Management System will be established to control and trace the HVAC system which is consist of AHUs, hot water boilers and hot water circulation pumps, chillers and chilled water pumps and the other mechanical equipments. This BMS carried out by Johnson Controls field equipments and controllers and software. DDC panel production, mechanical installation of the field equipments, cable connections, programming of the controllers and startup is made by us.
عدد نقاط التحكم 1.355 IO points
PRIVATE DEFALIFE HOSPITAL
الموقع GAZIANTEP - TURKEY
العام 2015-2016
حالة العمل DDC-MCC panels have been delivered to the site,
Mechanical installation works and cable end termination works for the field instruments are completed.
BMS has been delivered to the customer in 2016.
العمل المنفذ DDC panels production MCC panels production Mechanical installation and cable end terminations for the field instruments. All the engineering works included project, programming the controllers, designing the BMS HMI, test and start up and training.
عدد نقاط التحكم
PRIVATE SEZAR HOSPITAL
الموقع ADANA - TURKEY
العام 2016
حالة العمل The BMS has been completed and delivered to the customer in 2016.
العمل المنفذ The Building Management System will be established to control and trace the HVAC system which is consist of AHUs, hot water boilers and hot water circulation pumps, chillers and chilled water pumps and the other mechanical equipments. This BMS will be carried out by Johnson Controls field equipments and controllers and software. DDC - MCC panels production, mechanical installation of the field equipments, cable connections, programming of the controllers and startup has been made by us.
عدد نقاط التحكم
BESMAYA ELECTRICAL POWER PLANT
الموقع BAGHDAD - IRAQ
العام 2016-2017
حالة العمل HVAC BMS had been comleted in November, 2017.
العمل المنفذ Documentation, DDC and MCC panel production with Factory Acceptance Test, Programming the controllers and BMS HMI, and startup the HVAC system via BMS, Site Acceptance Test, Verification process for HVAC field instruments, Training for users,
عدد نقاط التحكم 2.600 IO and Bacnet Integrations
PRIVATE AKADEMI HOSPITAL
الموقع GAZIANTEP - TURKEY
العام 2016
حالة العمل The BMS has been completed in 2016.
العمل المنفذ The Building Management System will be established to control and trace the HVAC system which is consist of AHUs, hot water boilers and hot water circulation pumps, chillers and chilled water pumps and the other mechanical equipments. This BMS will be carried out by Johnson Controls field equipments and controllers and software. DDC panels production, mechanical installation of the field equipments, cable connections, programming of the controllers and startup has been made by us.
عدد نقاط التحكم
SARAYHAN THERMAL HOTEL / D BLOCK
الموقع CIFTEHAN / NIGDE - TURKEY
العام 2016-2017
حالة العمل The DDC and the MCC panels and the field equipments have been delivered to the site, cable terminations, programming and commissioning are completed. The project is complete at the end of year 2017.
العمل المنفذ The Building Management System is being established to control and trace the HVAC system which is consist of AHUs, and the other mechanical equipments. This BMS was carried out by Johnson Controls field equipments and controllers and software. DDC and MCC panels production, mechanical installation of the field equipments, cable connections, programming of the controllers and startup has been made by us.
عدد نقاط التحكم 300 IO points
PRIVATE ORTADOGU HOSPITAL ADDITIONAL FACILITY BUILDING
الموقع MERSIN - TURKEY
العام 2016-2017
حالة العمل the BMS has been completed and delivered to the customer in 2016.
العمل المنفذ Manufacturing the DDC and MCC panels
Preparing the cabling projects,
Mechanical installation for the field instruments, Cable end terminations, Programming and start up the HVAC BMS
عدد نقاط التحكم 300 IO points.
PRIVATE ALTINKOZA HOSPITAL BUILDING
الموقع YUREGIR / ADANA - TURKEY
العام 2016
حالة العمل The project has been completed at the end of 2017.
العمل المنفذ The Building Management System had been established to control and trace the HVAC system which is consist of AHUs, exhaust fans, operation theaters and the other mechanical equipments. This BMS was carried out by Johnson Controls field equipments and controllers and software. DDC-MCC panels production, mechanical installation of the field equipments, cable connections, programming of the controllers and startup is made by us.
عدد نقاط التحكم 450 IO points
SCIENCE AND TECHNOLOGY UNIVERSITY - BTU
الموقع ADANA - TURKEY
العام 2018
حالة العمل Three of the buildings are in our scope :
Engineering Faculty Building
Administratin Building ( Rectorate Building )
Dining Hall Building

HVAC BMS had been comleted in March, 2018.
العمل المنفذ The Building Management System had been established to control and trace the HVAC system which is consist of AHUs, Heat Recovery Units, Rooftop Unit and the other HVAC mechanical equipments. The BMS was carried out by Johnson Controls field equipments and controllers and software. DDC and MCC panels production, mechanical installation of the field equipments, cabling and cable connections, programming of the controllers and startup were made by us.
عدد نقاط التحكم 1.350 IO points and Bacnet integration points.